Each one in plain English, with the numbers worked through for a shareholder.
30 May 2022quarterly activities report● Neutral
Quarter to 30 April 2022: management focused on the OZ Minerals terms sheet. The revised West Kalkaroo gold PEPR was essentially finished but will not be lodged with DEM for now, pending OZ's study and option decision. Shareholder meeting planned for August.
OZ Minerals signed a conditional terms sheet for an option to buy 100% of Kalkaroo for $205m within up to 18 months, paying Havilah $1m a month. Up to $200m more is contingent ($65m, plus up to $135m). Needs Havilah shareholder approval.
Havilah signed a binding conditional terms sheet giving OZ Minerals an 18-month option to buy 100% of Kalkaroo for $205m, plus up to $200m contingent payments. OZ also funds up to $18m for copper exploration. Needs shareholder approval within 90 days.
Interim financial report for the half-year to 31 January 2022. Visible text covers only the cover, directors and principal activities, with no financial figures readable. Directors unchanged; focus is exploration and advancing West Kalkaroo.
Quarter to 31 January 2022: PEPR re-lodgement now targeted within a month, awaiting two consultant reports; mining study awaits contractor cost estimates. $600,020 raised via 3.53m shares at $0.17. Drilling is delayed by a compressor shipping hold-up.
Havilah answers an ASX 'aware' query about the 17 January Mutooroo results. It says the draft was circulated after the 14 January price rise, so the rise was unrelated, and the results were probably not material. It confirms Listing Rule 3.1 compliance.
First Mutooroo pre-feasibility open pit extension holes hit shallow copper-cobalt sulphide: 5m at 1.7% copper, 0.18% cobalt, and 5m at 1.01% copper. A new hangingwall lode was found. Further drilling follows in February 2022 once a new compressor arrives.
Havilah answers an ASX query about a share price rise from $0.175 to $0.21 on high volume on 14 January. It says it knows of no undisclosed information and has no explanation beyond analyst views that its market value undervalues its resources.
Havilah lodges its new Constitution, adopted as a special resolution (Resolution 7) at the 21 December 2021 AGM. Administrative filing; no commercial information.
AGM technical presentation recapping 2021: PEPR lodged March, to be relodged in Q1 2022, plus infill drilling and contractor and financier talks. Restates known progress and plans; no new results.
Quarter to 31 October 2021: West Kalkaroo PEPR will not be re-lodged with DEM until early 2022 because consultant reports are delayed, so approval is expected during 2022. Board final investment decision also 2022. Financing depends on approval and a feasibility study; RPM is updating the mining study.
9 Nov 2021asset acquisition disposition▲ GoodMajor
Havilah proposes sponsoring an IPO of its uranium assets in subsidiary NU Energy, raising at least $10m, with priority for shareholders and a planned in specie distribution of most NU Energy shares. Follows Aroha's May withdrawal. Subject to market conditions and a prospectus.
ASX paused trading in Havilah pending a further announcement; no reason is given in the text. It coincides with the uranium IPO release of the same date (inference).
Statutory Jobkeeper disclosure: Havilah received $90,000 for 10 individuals in FY2020 and $105,000 for 10 in FY2021, with no repayments. Administrative notice.
Corporate governance statement for the year to 31 July 2021, approved 25 October 2021. Routine disclosure of governance practices; no new commercial information.
Annual report for the year to 31 July 2021. Visible text is the cover, contents and key strengths only, restating Kalkaroo's 100.1Mt reserve and West Kalkaroo mining planned for 2022. No financial figures are readable here.
Presentation at the Copper To The World Conference restating the 1.3Mt copper resource, 2019 PFS figures and West Kalkaroo plan. It cites pre-tax NPV of A$1.16bn at recent long-term prices. No new results.
Quarter to 31 July 2021: DEM gave detailed PEPR feedback with no critical issues found, but approval will likely take at least two more months. Gold mine development is now aimed at 2022. Largely repeats the June-July drilling and Cockburn results.
Four RC holes at the Cockburn prospect, 45 km southwest of Broken Hill, found a 10-20m wide quartz-sulphide lode with copper and cobalt shown by handheld XRF. Lab assays are pending, so economic significance is unproven. At least 1.5 km of strike is to be tested.
East Kalkaroo drilling returned 39m at 1.62% copper and 59m at 0.83% copper. Havilah says it points to possible breccia-vein mineralisation below the current resource, with bulk underground potential. Gold pit development is aimed at 2022.
Infill holes at Kalkaroo hit copper sulphide of 57m at 1.24% copper and 0.89 g/t gold, and 54m at 1.20% copper. Havilah now says the gold project 'remains on track' to start in early 2022, later than the 2021 start previously aimed for.
Quarter to 30 April 2021: West Kalkaroo PEPR lodged, contractor and financier talks, six sterilisation holes and a preliminary model. Kalkaroo pre-tax NPV is said to exceed $1.1bn at longer-term prices in the 2019 PFS model. Cultural heritage surveys done for Grants and Mutooroo drilling.
Infill drilling at Kalkaroo returned 17m at 2.24 g/t gold and 46m at 0.49% copper; six sterilisation holes done. Preliminary model indicates robust gold economics, and Havilah intends to seek maximum debt funding. PEPR feedback so far only concerns the rehabilitation bond calculation.
12 May 2021material agreement termination▼ BadMajor
Aroha Resources withdrew from the February uranium MOU, ending the planned 25% stake, $500,000 payment and royalty. Havilah says it is considering its own sponsored IPO of the uranium assets, with priority rights for eligible shareholders, and will update in coming weeks.
Half-year report to 31 January 2021. Visible text is only the cover, directors' report introduction and forward-looking statements; the gold pit is still subject to a board investment decision, financing and approvals. No financial figures are readable here.
Havilah lodged the West Kalkaroo PEPR, described as the final permitting approval needed for the gold mine. The regulator indicates at least 3-4 months to assess, absent major revisions. Havilah will use that time on contractor, financing and plant design work.
Quarter to 31 January 2021: PEPR nearly ready, financier discussions started, Mincore cost inputs received, and 2% royalty eligibility. Two Croziers holes found only minor mineralisation. Shares issued: 19.3m via placements ($3.3m) and 16.0m via SPP ($2.7m), all at $0.17. Largely repeats earlier news.
Havilah signed a binding MOU giving Aroha Resources exclusive uranium rights over specified licences, conditional on an Aroha ASX IPO. Havilah would hold about 25% of Aroha, get $500,000 from IPO proceeds and a 1.5% royalty after $10m of sales. Lapses if no IPO within 12 months.
Three more RC holes in the Kalkaroo fault zone hit 16m at 1.31 g/t gold, 10m at 1.51 g/t gold and 13m at 1.37% copper. Mineralisation is now over 100m wide, and SA says Kalkaroo qualifies for a 2% royalty for the first five years of production.