Each one in plain English, with the numbers worked through for a shareholder.
18 July 2008regulatory community update▲ Good
Curnamona Energy accepts a new exploration licence, Yalkalpo, north of Oban along the same uranium trend. Historic drilling suggests uranium accumulation over at least 70 sq km. A second eight-wheel-drive rig is being commissioned, with drilling planned next quarter.
Havilah starts the planned 2,300m RC drilling programme at Prospect Hill tin, testing depth extensions of earlier tin hits. The aim is a deposit large enough for open-pit mining, against the existing inferred 172,000t at 1.15% Sn. Diamond drilling may follow depending on results.
11 July 2008regulatory community update▲ GoodMajor
PIRSA approves a 248.1 hectare retention lease over Oban uranium for Curnamona Energy (45.4% Havilah), after 15 months of process. This follows the public comment period. A mining and rehabilitation plan for the field leach trial must still be lodged; no resource is published.
Kalkaroo feasibility drilling reaches 183 holes, e.g. 78m at 0.56% Cu and 1.8 g/t Au (KKDD222). Mineralisation is now drilled over 3km, and an updated JORC resource model has started. The feasibility study stays on track for end 2008.
Havilah farms out seven non-core Curnamona tenements to Canopus Resources, which can earn 60% by completing a bankable feasibility study. Havilah gets 17.4% of Canopus at its IPO; shareholders get a priority offer of 1 Canopus share per 4 Havilah shares. Fits its copper focus.
March-quarter report: Glencore pays the second $7m tranche for the Kalkaroo feasibility study, with 89 more holes drilled in the quarter. Mutooroo is now targeting a shallow oxide copper resource suited to leaching. The Curnamona share distribution still awaits tax office advice.
Kalkaroo hole KKDD146 returns 38m at 2.13% Cu and 0.46 g/t Au, described as among the thickest and highest-grade copper intersections at the deposit. It lifts the 1.37% Cu of its earlier RC twin. Metallurgy is largely complete and resource calculations are approaching.
Geothermal Resources (63.6% Havilah) finishes two 250m Frome holes showing gradients of about 42°C/km. It now plans an 1,800m diamond hole 3km west of Frome 3, starting early in the second half of 2008, subject to permit and rig. This replaces the earlier 1,000m+ plan.
At the ASX's request, Havilah clarifies its 29 April Prospect Hill update: the 1 million tonne figure is only a drilling target, and there is no certainty drilling will exceed the existing inferred 172,000t at 1.15% Sn. No new results.
Chairman's conference presentation sets a target of 55,000t copper and 100,000oz gold a year from Kalkaroo, Mutooroo and Portia over three years, mostly starting with oxide ore. Feasibility studies are due end 2008. It largely restates known plans, with 81.9m shares on issue.
Havilah plans over 2,000m of further RC drilling at Prospect Hill tin next quarter, targeting 1 million tonnes of open-pit ore versus the existing inferred 172,000t at 1.15% Sn. Tin recoveries by gravity methods are good in early tests. This follows the earlier planned second round.
Kalkaroo feasibility drilling passes 130 holes, with new results such as 99m at 0.77% Cu and 0.75 g/t Au (KKDD144). Lab assay delays of several months are holding back reporting. New tests show flotation recoveries above 85% for mixed ore; West Kalkaroo resource calculations are expected to start within a month.
Lion Selection reports buying $0.1m of Havilah shares on market, lifting its holding to 18.6%. Lion first invested in 1997 at an average cost of 28 cents a share. It is a third-party holder notice, not company news.
Half-year report to 31 January 2008 largely restates operations: Glencore's $14m Kalkaroo feasibility funding with about 60 holes drilled, positive Mutooroo metallurgy, Portia native title and mining plan progress, and the Prospect Hill farm-in. Financial figures not visible in the supplied text.
Kalkaroo metallurgy confirms high recoveries: up to 90% copper and 80% gold from native copper ore, and up to 97% copper and 89% gold from primary sulphide. The chairman says it supports mining the oxide ore first. The feasibility study is due by end 2008.
Curnamona Energy's Oban field leach trial proposal and retention lease go out for public comment until 11 April 2008, after which PIRSA will assess it. Oban drilling has outlined over 2 sq km of mineralisation. This is a step in the pending permitting.
7 Mar 2008farm in farm out completion● NeutralMajor
The Mutooroo JV with Heilongjiang Resources is dissolved. HJR, which advanced $3m (about $2m spent), converts into 2 million Havilah shares plus 1.5m options. The low-capital direct-shipping idea is unlikely to be best, and Havilah keeps 100% of Mutooroo.
Slides from a chairman's talk to a South Australian mining chamber luncheon. The company says it summarises recent announcements; no new information is evident.
December-quarter report. Kalkaroo has about 60 holes done, with deep step-outs above orebody average grade, e.g. 113m at 0.63% Cu and 1.33 g/t Au. Mutooroo metallurgy is favourable and Portia native title is agreed. The Curnamona distribution awaits tax office advice.
Curnamona Energy (now shown as 45.4% Havilah) begins 2008 drilling in the Yarramba palaeochannel west of Oban, with 36 holes done and a few anomalous gamma readings. It rebuts criticism of the Oban leach trial permitting.
Geothermal Resources (63.6% Havilah) restarts Frome drilling with three more shallow holes of 200-300m. A 1,000m+ hole is planned for the first half of 2008, then a 3km+ hole later in the year, subject to results.
Kalkaroo drilling returns e.g. 100m at 1.13% Cu and 0.84 g/t Au (KKRC160), with four rigs on site; early tests recover over 40% of native copper by screening. Mutooroo metallurgy is positive. The tax office ruling on the Curnamona distribution is still awaited.
All nine AGM resolutions pass, including the capital reduction and director option grants. The chairman's address says Portia will be the first mine, Mutooroo the second, and Curnamona shares will be distributed. Largely restates known plans.
Havilah finalises a mining native title agreement with the Adnyamathanha claimants over Portia-North Portia, including Havilah shares (number not disclosed) plus training and employment. With the MARP lodged, a mining lease for the trial pit awaits PIRSA's grant.
September-quarter report. Proposes an in specie distribution of Curnamona shares worth about 30-40 cents per Havilah share, subject to AGM vote and tax relief. Prospect Hill hits 3m at 4.85% tin; two mining engineers hired; Curnamona stake now 47.7%.
Mutooroo feasibility drilling reaches 50 holes (7,921m) in 2007, with new footwall zones, e.g. 24m at 1.3% Cu (MTRC115) and 17m at 1.34% Cu (MTRC107). Early metallurgy shows over 99% recovery to concentrate. Deposit remains open to the north and at depth.
2007 annual report restates the year: Kalkaroo up 28% to 108Mt, Glencore funding for a 14% interest, Mutooroo feasibility, the $9.44m raising, and Portia bedrock gold. The chairman targets the Portia trial pit early in 2008 and first revenue next year.
Curnamona Energy drills 33 more Oban holes, extending uranium mineralisation several hundred metres south; the area is nearing 2 sq km. No JORC resource is possible until leach recoveries are proven; draft mining plan lodged with PIRSA.
Havilah farms into EL 3605 (Prospect Hill tin), able to earn up to 85% by completing a feasibility study. It holds an inferred 172,000t at 1.15% tin. A 1,100m drilling programme starts next week. A new project outside the core assets.
Geothermal Resources' shallow Frome holes record up to 45°C at 440m (Frome 3), with 40°C+ at 500m across at least 400 sq km. Company infers over 200°C is likely near 4,000m (an inference). Further shallow holes come before deeper tests.