27 Oct 2009annual report● Neutral
Havilah's 2009 annual report restates the Kalkaroo 62Mt resource, the granted Portia mining lease, Oban and Frome resources. It says Kalkaroo should move toward mining next year and exploration will resume. It lists Geothermal Resources at 58%, down from 63.6%.
Curnamona Energy (Havilah 45%) repeats its Oban update: the trial plant design costs at least $3m, core recovery tests come first, and monitor holes show ore-grade intersections outside the 8.2Mt resource. Regional drilling stays paused. Largely repeats the 6 October update.
Curnamona Energy (Havilah 45%) has designed the Oban trial plant, costing at least $3m, but will test resin recovery on core samples before committing. Monitor holes show ore-grade intersections outside the current resource. Regional drilling is paused.
Activities update: Kalkaroo feasibility is planned for completion by end of October. Portia needs an approved MARP before the mining lease is granted. Havilah is still seeking a Mutooroo funding partner, and has a first-pass look at a new Lilydale iron ore prospect.
June-quarter report: Kalkaroo feasibility, now due end of October 2009, shows a 10-stage pit to 205m depth. PIRSA has offered a 1,745 Ha mining lease over Portia and North Portia. Resource drilling started at North Portia. This delays the earlier mid-year feasibility target.
Downhole logging in 24 new holes at Oban (Curnamona, Havilah 45%) shows the uranium is in equilibrium, so the earlier gamma results can be relied on. The field trial is budgeted at least $3m, and the plant would make about 50t a year.
The Pernatty Lagoon hole ended at 1,838.8m, with magnetite alteration and minor copper veining from 1,656m. No economically significant zones are visible. Red Metal will seek joint venture partners; an electromagnetic survey and assaying follow.
Portia base-of-Tertiary gold gets an Inferred resource of 720,000t at 2.9 g/t for 67,000oz, using a 60 g/t high-grade cut. Preliminary designs suggest a trial pit could yield about $10m cash surplus at A$1,000/oz. Permitting continues.
Drilling starts on a 7km by 3km magnetic and gravity target at Pernatty Lagoon, Olympic Dam domain, by extending a hole 800-900m to about 1,600-1,700m. Red Metal holds 85.07% and Havilah 14.93%, and Havilah chose to fund its share.
Curnamona Energy (Havilah 45%) books a first Inferred resource at Oban: 8.2Mt at 260 ppm eU3O8 for 2,100t eU3O8. Recovery is unproven until the field trial; the company aims for up to 200t a year by late 2010 if the trial succeeds.
29 May 2009quarterly activities report● NeutralMajor
March-quarter report: Kalkaroo resource update done; Portia mining lease proposal is out for comment; Oban trial approvals received. Canopus could not list on the ASX and its farm-in was terminated 9 April 2009, so Havilah resumes responsibility for the tenements. Frome 13 finished at 1,809m, 96°C.
Frome 13 passes 1,650m toward 1,800m, with 89°C measured at 1,600m. This is a gradient slightly higher than Frome 12. Geology is as predicted and the hole is on time and budget.
Kalkaroo updated measured resource is 62Mt at 0.55% copper and 0.44 g/t gold, about 341,000t copper. This replaces the 70Mt scoping figure, with higher copper grade but lower tonnage from lower density. Feasibility is still due mid-year.
Geothermal Resources (63.6% Havilah) is drilling Frome 13 at 650m toward 1,800m, about 26km north of Frome 12. A temperature of 50.5°C at 642m shows a gradient above 40°C/km, comparable to Frome 12. No final result yet.
Havilah lodges its Mining Lease Proposal for the Portia gold project with PIRSA; public comment closes 30 April 2009. A native title agreement is already in place. The planned trial open pit still depends on financing.
PIRSA approves the mining and rehabilitation program for Curnamona Energy's Oban uranium field trial (Havilah owns 45%). The trial still needs a rehabilitation bond and EPA approvals; funds are in hand. This resolves the pending PIRSA approval thread.
Half-year to 31 January 2009: Kalkaroo feasibility now expected by mid-2009. The Prospect Hill 24-hole, 2,231m round did not significantly expand the tin, which is confined to a narrow, discontinuous lode. Mutooroo stays suspended. Financial figures are not visible in the text.
At the ASX's request, Havilah amends its quarterly report: the claim of about 1 million ounces of gold at Kalkaroo rests on a 2006 JORC measured resource of 85Mt at 0.4 g/t gold and 0.4% Cu (1.09m oz). No new resource.
Notice that the escrow on 2,000,000 Havilah shares held by Heilongjiang Resources ends on 12 March 2009. These are the shares issued when the Mutooroo joint venture dissolved. Administrative only.
December-quarter report: Kalkaroo feasibility progresses, with West Kalkaroo gold such as 58m at 2.2 g/t. Havilah says Mutooroo remains suspended while it seeks a strategic partner. It still awaits approval for the Portia trial pit. Frome 12 temperature of 93.5°C is repeated.
Havilah issues a competent person statement for the 2008 annual report, naming Drs Johnson and Giles. Administrative only, with no new results or figures.
All four AGM resolutions pass. The chairman says Mutooroo activity was suspended after the September credit crisis, to focus on Kalkaroo, where Glencore stays committed. Prospect Hill is lower priority, and the Curnamona distribution was dropped.
Frome 12 stops at 1,761.2m, short of the planned 1,800m, after 290m of coring in granite. Bottom-hole temperature is 93.5°C, with gradient similar to Frome 3, suggesting temperatures approaching 200°C at 4km. The granite shows sub-horizontal fracturing. Decision on a production hole is still pending.
September-quarter report: Havilah cuts spending and focuses on the Glencore-funded Kalkaroo feasibility study. Kalkaroo drilling is complete at 219 holes and 38,674m, and an updated JORC resource model is due early 2009. The Curnamona distribution is deferred. Frome 12 passes 1,650m.
14 Nov 2008asset acquisition disposition● NeutralMajor
Directors drop the planned in specie distribution of about 24m Curnamona Energy shares, which no ATO ruling arrived for by the March cut-off. They cite changed markets and prefer to keep the 45.4% stake, which may later pay dividends. This ends the open demerger thread.
Frome 12 reaches about 1,300m with no trouble, a recorded 78.5°C at 1,266m. The company says this is consistent with a predicted 200°C or more at 4km depth. Planned depth is still 1,800m. No final result yet.
2008 annual report: the chairman says Kalkaroo and Mutooroo remain viable despite market turmoil, and the company is funded to finish feasibility studies. Portia will be mined with North Portia rather than stand-alone. Kalkaroo feasibility is expected in the New Year.
Geothermal Resources (63.6% Havilah) starts drilling Frome 12, planned to 1,800m, its deepest Frome hole. Bottom-hole temperature will decide whether a large production hole to 3-4km is drilled. The $2.4m REDI grant matches company funding. Follows the earlier planned 1,800m hole.
June-quarter report: Mutooroo drilling (9,000m, ~100 holes) shows oxide copper such as 37m at 1.34% Cu, but bottle-roll tests recover only about 40% copper. Mutooroo feasibility is now due Q1 2009. Kalkaroo drilling is largely complete, and Frome deep hole is about to start.
Curnamona Energy (45.4% Havilah) reports a new area of sand-hosted uranium west of Oban, over 60,000 sq m so far. Best hole CEY292 has 5.2m above 100ppm eU3O8 (0.21 metre-percent). More holes follow; the company says it has funds for the field leach trial.