Each one in plain English, with the numbers worked through for a shareholder.
25 May 2015investor presentation● Neutral
Updated company presentation for a PhillipCapital roadshow in Singapore and Hong Kong, plus new Portia videos. Shows cash $2.9m, debt $0.8m and market cap $52m, with a list of major shareholders. No new results.
Havilah says adverse weather in New South Wales has not affected Portia, with a perimeter bund built around the pit and dewatering working. CMC plans a second 250 tonne excavator within weeks. Reassures shareholders; no change to timing.
Half-year accounts to 31 January 2015 largely recap known events: the CMC contract, Kalkaroo public comment, and the $2.1m Kalkaroo Station purchase. Overburden removal started 30 March; first ore is expected by June 2016. Financial figures are not visible in the text provided.
Conference presentation on Portia, which began open pit mining on 30 March 2015. Site works are largely complete, with first gold ore still targeted by 1 July 2016. Repeats the earlier 50:50 CMC deal and the 67,000oz resource; no new results.
Invitation and slides for shareholder presentations on Havilah and the Portia mine. Slides restate known points: cash $2.9m and debt $0.8m at 31 Jan 2015, market cap $41m, and a prospect of over $40m gross cash flow in 2016. No new results.
Invitation to shareholder presentations in Adelaide, Melbourne and Sydney on the company and the Portia development, with the Adelaide session on 27 March to be videoed. Administrative notice with no new results.
Havilah highlights a local newspaper article on Portia progress, with the contractor saying 12 million tonnes of overburden must be moved and ore mining is on budget for July 2016. Dewatering system nearly finished by Havilah's own crew.
Question and answer document from broker Phillip Capital, drawn from a discussion with the Managing Director on the Kalkaroo updated mining study. It restates the 2 March study content; no new figures in the text provided.
Havilah adopted a new constitution and changed its name to Havilah Resources Limited, approved at the 16 December 2014 AGM. ASX effective date is 11 March 2015; the HAV code is unchanged. Administrative only.
Updated Kalkaroo mining study targets a 2016 go-ahead. Lower-capital start-up costs A$83m, 17.5-year life; high-capital A$340m, 14 years. Resource is 620,000t copper and 2Moz gold. Models assume US$2.80/lb copper and US$1,300/oz gold; financing and permits are still needed.
January quarter report: Portia funding secured without dilution or debt, Kalkaroo proposal public comment closed, MMG drilled 12 more holes, and the station purchase settled. Maldorky native title talks with Wilyakali did not advance. Largely repeats earlier news.
Question and answer document from broker Phillip Capital, based on an interview with the Managing Director, on how the Portia mining and funding contract works. It gives background on the January agreement; no new results disclosed in the text provided.
A $1.954m rehabilitation bond guarantee was lodged, backed by contractor CMC, satisfying one condition of the Portia contract. DSD was notified mining starts, with overburden removal targeted for mid-March. Moves Portia from approved to under way.
Havilah signed a Portia mining and funding contract with Consolidated Mining & Civil, which funds all mining and the $1.95m rehab bond guarantee in return for 50% of gravity gold revenue. No raising needed; first ore to plant by June 2016. Conditions precedent remain.
AGM presentation recaps 2014 milestones and says a 50:50 Portia mining contract is substantially finalised but not signed. Havilah says no capital raising is needed for its processing role, with gold income expected in 2016. Mostly repeats known facts.
Kalkaroo's 1,400-page mining lease proposal passed DSD's adequacy check and was posted for public comment, resolving the thread open since the September check. Next step is a PEPR; native title talks with Adnyamathanha continue.
Joint venture partners presented a new high-grade tin lode, Fly Hill, at Prospect Hill (up to 50% cassiterite). Its grade and size are unknown, as native title claims have blocked detailed work for two years. Existing Inferred resource is 172,000t at 1.15% tin.
October quarter report: Portia approval, Kalkaroo Station purchase and Birksgate discovery. Portia mining is intended to start in Q1 2015, subject to financing and a mining contract. Kalkaroo proposal passed DSD's adequacy check on 3 September; more information was requested.
2014 annual report restates the year's progress: Portia mining approval, Kalkaroo Station purchase, Maldorky pilot plant result and the Birksgate discovery. Cash was $4.9m at end September 2014, after the station purchase. Largely repeats prior announcements.
Portia gold project's PEPR was approved by DSD, giving full operational mining approval. This resolves the long-running approval thread. Conditions include a ~$1.9m rehabilitation bond. Havilah aims to settle financing and mining contract arrangements before year-end.
20 Oct 2014capital raising announcement▲ GoodMajor
Havilah placed 5.96m shares at $0.14 with free $0.30 options to large holders who were scaled back in the rights issue, raising $0.8m after costs. Total raised is about $5.0m, taking shares on issue to 156.4m.
What it means for a shareholder
6.0m new shares at $0.140 to raise about $800,000. Shares on issue before the raise aren't in the record, so the dilution can't be worked out.
MMG drilling made a new copper discovery at Birksgate: 10.9m at 0.84% Cu, 0.64 g/t Au from 209.5m. Nine of ten Eurinilla holes hit Kalkaroo-style mineralisation, best 6m at 5.3% Cu. Follows the 2014 MMG program under the joint venture.
Havilah agreed to buy Kalkaroo Station, the pastoral property hosting its Kalkaroo copper-gold project, for $2.1m, with $1.0m deferred to April 2015. Ownership removes land access negotiation risk. Subject to ministerial consent; funded from existing working capital and R&D refunds.
July quarter report: rights issue raised $4.2m, Maldorky proposal public comment closed, and the Portia revised PEPR was lodged. Kalkaroo final draft proposal had no timing indication from DSD after five weeks. Investor talks continue.
Rights issue finalised: 30.08m new shares and 30.08m free $0.30 options issued, raising $4.2m, oversubscribed by about 32%. Shares on issue rise to 150.4m. Over 700 holders took part.
What it means for a shareholder
30.1m new shares at about $0.1396 to raise about $4.2m. Shares on issue before the raise aren't in the record, so the dilution can't be worked out.
25 Aug 2014capital raising announcement▲ GoodMajor
The 1-for-4 rights issue at $0.14 closed oversubscribed, raising the full $4.2m target. Applications were for 39.4m shares against 30.1m available, about 131%, so top-up requests will be scaled back. Resolves the raising launched on 17 July.
What it means for a shareholder
39.4m new shares at about $0.1066 to raise about $4.2m. Shares on issue before the raise aren't in the record, so the dilution can't be worked out.
Maldorky pilot plant made 65% Fe iron concentrate. Portia PEPR re-lodgement is due the following week after the water-reinjection trial was confirmed viable, with mining hoped before end-2014. Final Kalkaroo mining proposal lodged; an Environmental Manager was hired.
Managing Director Dr Chris Giles presented to shareholders during the rights issue offer. It restates known plans: four projects to develop over five years, partners to fund project equity, and cash of $2.3m at April 2014. No new results.