30 Nov 2010joint venture update▲ GoodMajor
Mitsubishi Corporation committed a further A$40M of a A$50M 2011 exploration program plus up to A$50M of Ungani-area development costs, on top of its existing A$22.4M 2010 program commitment - a strong vote of confidence in the Canning Superbasin.
Nangu-1 (spudded 28 November, Mitsubishi funding 80%) reached 310m, targeting wet gas in the Grant Formation sands (P50 estimate 1 MMbbl condensate/15 Bcf gas) updip from a 1965 well with good shows.
Rig-up began at Nangu-1, the 2010 campaign's fourth well and the second under the Mitsubishi Joint Exploration Program, targeting a modestly-sized wet gas/condensate structure Buru said could open up a regional gas-gathering project if successful.
Oil Basins Limited earned a 100% beneficial interest in the Backreef Area after drilling Backreef-1 past 1,500m, issuing 2 million shares to Backreef Oil Pty Ltd to settle its interest - basin-adjacent, Buru remains permit titleholder.
Paradise-1 reached 1,119m with continued (partially cured) lost circulation; oil was still being observed on shakers and drill pipe, though its origin and significance remained unclear.
Yulleroo-2's logging runs finished with still no stabilised flow rate, though rising shut-in pressure buildup indicated the well continued to clean up; it was also flowed through a separator to sample liquids.
Pancontinental's own report of the Stokes Bay-1 test results matched Buru's: 2,760 barrels of all-water fluid recovered, no hydrocarbons, well suspended.
Yulleroo-2's stimulation program re-established gas flow after nitrogen lifting but couldn't hold a stabilised rate over roughly six hours; the well was shut in for pressure measurement and wireline logging.
Yulleroo-2's three planned stimulation zones (3,100m/2,980m/2,850m) were all completed with no problems; the well flowed unaided for 16 hours before being shut in for wireline logging as part of the standard clean-up process.
Paradise-1 drilling resumed after curing lost-circulation zones, while Yulleroo-2's first two frac stages showed encouraging pressure signs (wellhead pressure over 4,500 psi) ahead of a planned flow test.
Yulleroo-2's stimulation program began, perforating the first of three zones (3,100m) under the Buru-Mitsubishi Joint Exploration Program (Mitsubishi funding 80% of costs).
ASX cancelled and re-released an announcement that had been misfiled under Buru Energy's code (it belonged to Burleson Energy Limited, an unrelated company); no substantive Buru Energy content was involved.
New Standard Energy reported a successful frac at its Heintschel #1 well, with healthy initial hydrocarbon flow rates while the well continued cleaning up - basin-adjacent context.
Buru Energy reported $33.8M cash on hand at the end of the quarter ended 2010-10-25, having used $5.5M in operating cash flow that quarter. Against its own $5.0M forecast for next-quarter outflows, that implied roughly 6.8 quarters of funding on hand.
Buru began stimulating and testing the Yulleroo-2 gas well (permit EP391) under its June 2010 Farm-in Agreement with Mitsubishi Corporation (MC) - MC was funding 80% of a $22.4 million 2010 Canning Basin work program to earn an initial 40% interest across most of Buru's permits, the first year's cost-carry tranche under the broader up-to-$152.4 million MC farm-in.
Buru advised that further testing of Stokes Bay-1 (R1 permit) would begin mid-November 2010, using the coiled tubing unit mobilising for the Yulleroo-2 frac.
Paradise-1 spudded at 18:00hrs on 18 October 2010 - the third well of the 2010 campaign and the first well of Buru's new Joint Exploration Program with Mitsubishi Corporation - testing a stacked-reservoir prospect with P50 potential of about 16 million barrels of oil plus over 200 Bcf of gas.
Paradise-1 neared spud while the Yulleroo-2 flow test slipped to around 25 October after the stimulation contractor's equipment was stranded by Queensland floods; a seismic program continued in parallel to firm up targets for the 2011 six-well program.
Buru's rig moved to Paradise-1, the first well drilled under its new Joint Exploration Program with Mitsubishi Corporation (which funds 80% of costs as part of a $22.4 million 2010 commitment to earn an initial 40% interest across most of Buru's permits); the target zone had shown an untested 11-metre oil column in a nearby 2007 ARC Energy well (Valhalla-1) that was never flow tested.